Logo

Pebble Bed Micro Model Start-up

The PBMM (the world's first closed cycle multi-shaft gas turbine test rig) was developed to demonstrate the operation of a three-shaft, pre- and inter-cooled recuperative Brayton cycle in order to gain a better understanding of its dynamic behavior. The entire cycle was designed, simulated and commissioned with Flownex within 9 months at a cost saving of $48 million.